Avanti Helium (TSXV: AVN) (OTC: ARGYF) said Monday construction and development on its Sweetgrass helium Project in Montana is advancing toward the assembly and commissioning of its helium recovery facility. Construction of the main processing facility building is underway, with completion currently anticipated in early November 2026. The project has advanced through well-site infrastructure, gathering pipeline construction, equipment fabrication and site preparation, the company said, adding that the next development phase is the delivery, installation and assembly of its helium recovery unit (HRU).